Toledo Waterways Initiative | Home

S-4: Woodsdale SSES and Inflow Reduction

Status: Under Design

Waterway: Swan Creek

Location: To Come

Description:

  • Perform flow monitoring to determine if an SSES is required for this area, which was monitored as part of the 2003 flow monitoring with inconclusive results
  • Previous sewer-separation project appears to have completed separation in the street right of ways, although private properties were not addressed
  • Separate storm and sanitary sewers already in use, therefore private inflow source removal recommended as the most cost effective option
  • Plan will eliminate discharge of sanitary sewage into the Maumee River and reduce peak flows into the Swan Creek Interceptor Sewer

Potential Dates and Duration:

  • Initiate Construction: Early 2011
  • Construction Complete: Winter 2012

Want Additional Information?

Return to Top